Anticipated Bridge Construction Schedule 2020
Posted on: October 25, 2019 - 11:59am
Please see the anticipated construction schedule for bridge preservation work on Boscawen bridges located on US Route 4 over River Road and Tremont Street over the Contoocook River. The Select Board agreed that "Alternative 2" would have the least long-term impact on travel in Boscawen. This alternative shortens the construction schedule from 34(+/-) weeks to 25 weeks(+/-).
**Please note that the start and end dates are relative and actual dates have not been decided yet.**