Paving Update 8/2/19

It’s been another productive week. The traffic circle has been completed, the repair at the signals has been completed, and the stretch between the two has also been completed. With that, the night paving has wrapped up.

Now onto the day paving. The plan as of now is to begin paving downtown Boscawen and US-3 towards Franklin on Tuesday. Pike will be having R&D doing the paving work. It is expected that Boyce Road and NH-127 could begin seeing new asphalt as early as Aug 14.

Pike will be attempting to schedule shoulder gravel for the completed sections in the coming weeks.