Tremont Bridge Schedule

Beginning May 8, 2020

On Monday at 8:00 am the signals on the Tremont Street Bridge will be activated.

Today, 5/8/20:

               ] Install balance of signal signs and bag

               ] Put lights on flash for the weekend

               ] Put in the 3 stop bars that are required

Monday, 5/11/20:

               ] 7:00am, activate detour and close down Maccoy Street, uncover all signal signs

               ] 8:00am, turn on signals and go one way traffic (using south side of bridge)

               ] Place new white line tape

               ] Place blackout tape for lane lines

               ] Switch all traffic into the northern side of bridge (all traffic traveling on the northern side of bridge now: upstream)

               ] Replace cones with barrels

               ] Install attenuator barrels on one end

Tuesday, 5/12/20:

               ] Set in all barrier and second attenuator barrel system

Wednesday, 5/13/20:

               ] Start installing bracing for bridge barrier