On Monday at 8:00 am the signals on the Tremont Street Bridge will be activated.
Today, 5/8/20:
] Install balance of signal signs and bag
] Put lights on flash for the weekend
] Put in the 3 stop bars that are required
Monday, 5/11/20:
] 7:00am, activate detour and close down Maccoy Street, uncover all signal signs
] 8:00am, turn on signals and go one way traffic (using south side of bridge)
] Place new white line tape
] Place blackout tape for lane lines
] Switch all traffic into the northern side of bridge (all traffic traveling on the northern side of bridge now: upstream)
] Replace cones with barrels
] Install attenuator barrels on one end
Tuesday, 5/12/20:
] Set in all barrier and second attenuator barrel system
Wednesday, 5/13/20:
] Start installing bracing for bridge barrier