Paving Update - 7/19/19
Posted on: July 19, 2019 - 11:42am
It has been a busy week for the crews on the road. The traffic circle has been milled out, the inlay for US-4 from the Park-&-Ride to Boyce Rd has been completed, and US-3 south of the signals is mostly complete.
The signaled intersection with US-3 should be completed early next week, and the paving of the wearing course will begin on US-4 from the Park-&-Ride to Boyce Rd.
Once those two sections are completed, Pike plans to pave the 1 mile stretch between the circle and the lights, and then the traffic circle.